The Administration recommends that the Board of Education ratify and authorize the execution and performance of an amended contract by The School District of Philadelphia, through the Superintendent or his designee, subject to funding, as follows:
With:
O and S Associates
Purpose:
To extend the time and increase the fee for O and S Associates, for professional design services provided for the Bayard Taylor Elementary roof replacement
Original Start Date: 10/26/2018
Original End Date: 8/20/2020
Amended End Date: 4/30/2023
Currently Authorized Compensation: $69,750
Additional Compensation: $44,250
Total New Compensation: $114,000
Location(s): Taylor, Bayard Elementary School
Description:
The Office of Capital Programs is requesting a fee increase for the architect of record, O & S Associates, for professional design services provided for the Bayard Taylor Elementary roof replacement project. The additional design fee was necessitated by the increase from the estimated project cost from $910,000 to $1,500,00 due to increased scope. The resulting design fee increased from $69,750 to $114,000. The contract scope was increased which required a construction time extension. The administrative design services period have been extended to align to the new construction completion date.
Guardrail 1: Welcoming and Supportive Schools - Every school will be a safe, welcoming, and healthy place where our students, staff and community want to be and learn each day.
Related resolution(s)/approval(s):
July 19, 2022; No. 20
Funding Source(s):
FY23 Capital Budget