Action Item - 12.

Title: Capital Award for Marshall, John Elementary School, Chase, Fox Elementary School, Elkin, Lewis Elementary School, Comly, Watson Elementary School ($9,121,677)

Board of Education Meeting Date:
  11/18/2021

Action under consideration

 The Administration recommends that the Board of Education authorize The School District of Philadelphia, through the Superintendent or his designee, to execute and perform separate contracts with the lowest responsible bidders, subject to funding, as follows:

 With:

TE Construction

Robert Michaels & Associates

Dolan Mechanical, Inc.

Madden Electrical

Gem Mechanical

Lorenzon Brothers Company



 Purpose:

General, Mechanical, Plumbing, and Electrical Contracts

 Start date: 11/21/2021

 End date: 6/30/2025
 Compensation not to exceed: $9,121,677 
 Separate Compensation by Vendor:

TE Construction - General Contract - Building Envelope at Fox Chase; $2,241,000

Robert Michaels & Associates - General Contract – HVAC replacement at Elkin; $687,000

Dolan Mechanical, Inc. - Mechanical Contract – HVAC replacement at Elkin; $3,481,000

Madden Electrical - Electrical Contract – HVAC replacement at Elkin; $777,777

Gem Mechanical - Plumbing Contract – HVAC replacement at Elkin; $178,000

TE Construction - General Contract – Window Replacement at Comly;  $1,387,000

Lorenzon Brothers Company - General Contract – Interior Door replacement at Marshall; $369,900


 Location: 

Fox Chase School; Elkin, Lewis School; Comly, Watson School; Marshall, John School



 Renewal Options:  No

 Description:

The Office of Capital Programs has identified various capital projects at multiple school locations based on the capital budget call and the facilities assessment report. The projects recommended for contract award were identified in the approved FY22 capital budget. The projects were publicly advertised and the lowest responsible bidders are recommended for contract award. The District design, construction, and project management teams have developed a site specific construction phasing plan in collaboration with principals and contractors for the site improvements. This plan ensures adequate time and sufficient swing space has been identified for the safety of students and staff. The work will be monitored daily by an inspector, project manager and construction manager to ensure the contractors meet the established budget and schedule. This work is in support of the Operations Division goal of providing a safe and healthy learning environment for all students.

 

Guardrail 1: Welcoming and Supportive Schools - Every school will be a safe, welcoming and healthy place where our students, staff and community want to be and learn each day. 



 Funding Source(s): 
FY 22-23 Capital Budget

 Office Originating Request: Operations - Capital Programs