| | | | | | | | Action Item - 15.
Title: Amendment of Contract with Various Firms for Supplemental Professional Architectural Services ($5,000,000)
Board of Education Meeting Date: 11/18/2021
|
| | | | | | | | Action under consideration
| The Administration recommends that the Board of Education authorize The School District of Philadelphia, through the Superintendent or his designee, to execute and perform an amendment of a contract, subject to funding, as follows:
| | With:
Kimmel Bogrette Architecture + Site
Crabtree, Rohrbaugh & Associates, Inc.
USA Architects, Planners + Interior Designers, P.A.
Vitetta Group, Inc.
Lan Associates, Inc.
Schrader Group Architecture, LLC
The Sheward Partnership, LLC
Johnson, Mirmiran, & Thompson, Inc.
BWA Architecture and Planning, LLC
Gannett Fleming, Inc.
Godshall Kane O’Rourke Architects, LLC
Atane, LLC (MBE)
Blackney Hayes Architects, P. C.
DLR Group
DI Group Architecture, LLC
| | Purpose: Additional time and funding for professional architectural design services
|
|
| | | | | | | | | Original Start Date: 12/13/2019
| | Current End Date: 12/13/2022
|
|
| | | | | | | | | Amended End Date: 12/13/2024
|
|
| | | | | | | | | Currently Authorized Compensation: $5,000,000
| | Additional Compensation: All entities will be paid out of the additional aggregate amount not to exceed $5,000,000 and new total aggregate amount not to exceed $10,000.000.
| | Total New Compensation: $10,000,000
|
|
| | | | | | | | | Description:
The Office of Capital Programs requests a time extension and additional funding for the supplemental professional architectural design contract. The additional time and funding are necessary to complete the work, which was delayed due to setbacks and delays related to the pandemic and the Covid-19 restrictions beginning in the spring of 2020. The amendment will allow for the completion of the required design documentation and permitting for projects identified in the approved Capital Improvement Plan (CIP). Each contract will include funding to initiate design services for architectural projects. To expedite this process, utilization of a pool of qualified firms is the most efficient way for the District to complete design activities in order to meet the project timelines. The approved firms’ services will be evaluated based on their ability to meet project milestones and remain within the approved budget. The work is in support of the Operations goal of providing safe, healthy and welcoming learning environments all students.
Guardrail 1- Welcoming and Supportive Schools Every schools will be a safe, welcoming and healthy place where our students, staff and community want to be and learn each day.
|
|
| | | | | | | | | Related resolution(s)/approval(s): December 12, 2019; No. 16
|
|
| | | | | | | | | Funding Source(s): FY 21-22 Capital Budget |
|