| | | | | | | | Action Item - 17.
Title: Capital Award for Various Locations - Lorenzon Brothers Company, TE Construction Services, LLC, Magnum, Inc., John J Bee, Inc., Palman Electric, Inc. ($3,977,731)
Board of Education Meeting Date: 4/22/2021
|
| | | | | | | | Action under consideration
| The Administration recommends that the Board of Education authorize The School District of Philadelphia, through the Superintendent or his designee, to execute and perform separate contracts with the lowest responsible bidders, subject to funding, as follows:
| | With:
Lorenzon Brothers Company
TE Construction Services, LLC
Magnum, Inc.
John J Bee, Inc.
Palman Electric, Inc.
| | Purpose:
General Contracts, Plumbing and Electrical Contracts |
|
| | | | | | | | | Start date: 4/23/2021
| | End date: 10/19/2023
|
|
| | | | | | | | | Compensation not to exceed: $3,977,731
|
|
| | | | | | | | | Separate Compensation by Vendor:
Lorenzon Brothers Company - General Contract - Exterior Door Replacement at Mitchell; $443,000
TE Construction Services, LLC - General Contract - Elevator Replacement at Webster; $442,000
Magnum, Inc. - General Contract - New Athletic Fields and Stadium Renovations at Lincoln; $2,497,000
John J Bee, Inc. - Plumbing Contract - New Athletic Fields and Stadium Renovations at Lincoln; $99,000
Palman Electric, Inc. - Electrical Contract - New Athletic Fields and Stadium Renovations at Lincoln; $496,731
|
|
| | | | | | | | | Location: Lincoln, Abraham High School; Mitchell, S. Weir Elementary School; and Webster, John H. School
|
|
| | | | | | | | | Description:
The Office of Capital Programs has identified various capital projects at multiple school locations based on the capital budget call and the facilities assessment report. The projects recommended for contract award were identified in the approved FY21 capital budget. The projects were publicly advertised and the lowest responsible bidders are recommended for contract award. The District design, construction, and project management teams have developed a site specific construction phasing plan in collaboration with principals and contractors for the site improvements. This plan ensures adequate time and sufficient swing space has been identified for the safety of students and staff. The work will be monitored daily by an inspector, project manager and construction manager to ensure the contractors meet the established budget and schedule. This work is in support of the Operations Division goal of providing a safe and healthy learning environment for all students.
|
|
| | | | | | | | | Funding Source(s):
FY 21-23 Capital Budget |
|
| | | | | | | | | Office Originating Request: Operations - Capital Programs
|
|
|